AE - Brothers Building Co of Nantucket v Yankow (12/11/2002)

Forum rules
The information given on this page is for educational and informational purposes only, and does not constitute any legal or tax advice or opinion. This page is meant to give a quick start to research by other professionals, but it should absolutely not be relied upon for any purposes whatsoever. Additionally, this page is kept current only as our time allows, and the information given here may not be current. We make NO GUARANTEES as to the accuracy of the information herein and you should not rely on it. Even professionals who use this information must independently verify whether it is correct and current. Nothing in the information given below should imply that the drafters of this webpage are admitted to practice law in the referenced state or have any special expertise in the areas listed. Nothing herein should be construed as a solicitation by the drafters of this website to practice law in the referenced state. Persons desiring planning should contact a licensed attorney or other appropriate planning professional in this state. Certainly, nothing herein is any substitute for the services, advice, or counsel of a properly licensed attorney in the relevant state!

AE - Brothers Building Co of Nantucket v Yankow (12/11/2002)

Postby Riser Adkisson LLP » Wed Jun 03, 2009 2:42 pm

Brothers Building Co. of Nantucket, Inc. v. Yankow
779 N.E.2d 991 (Mass.App. 12/11/2002)

Massachusetts Appeals Court

No. 01-P-526

56 Mass.App.Ct. 688, 779 N.E.2d 991, 2002.MA.0000587
December 11, 2002

BROTHERS BUILDING CO. OF NANTUCKET, INC., & ANOTHER*FN1
v.
KEITH YANKOW & ANOTHER*FN2; RICHARD C. BROTHERS, THIRD-PARTY DEFENDANT.

Civil action commenced in the Superior Court Department on April 29, 1998. The case was heard by
Vieri Volterra, J., and counterclaims and a third-party complaint were heard by Robert Malcolm
Graham, J.

James T. Ranney for Keith Yankow & another.

Michael G. West for Brothers Building Co. of Nantucket, Inc., & others.

Present: Brown, Greenberg, & Mason, JJ.

The opinion of the court was delivered by: Mason, J.

Nantucket.

October 4, 2002

Arbitration, Confirmation of award, Authority of arbitrator. Practice, Civil, Counterclaim and
cross-claim.

The plaintiffs, Brothers Building Co. of Nantucket, Inc. (Brothers Nantucket), and Brothers
Building Co., Inc. (Brothers Vermont), brought this action pursuant to G. L. c. 251, §§ 12 and
13, to vacate or modify an arbitration award. The award found the plaintiffs jointly liable to
the defendants, Keith and Robin Yankow, for damages in the amount of $49,900 that the Yankows had
suffered as a result of the plaintiffs' failure to perform certain renovation work in accordance
with an agreement between Brothers Nantucket and the Yankows. A Superior Court judge (motion
judge) denied the plaintiffs' motion to vacate or modify the award and allowed a motion by the
Yankows to confirm the award. Following a subsequent bench trial, a different Superior Court
judge (trial judge) dismissed various counterclaims and a third-party complaint that the Yankows
had brought.

On appeal, the plaintiffs claim that the motion judge erred in confirming the arbitrator's award
because, among other things, it imposed liability on Brothers Vermont even though it was not a
party to the agreement. The Yankows also appeal, claiming that the trial judge erred in
dismissing their counterclaims and third-party complaint.

We conclude that the arbitrator was without authority to impose liability on the nonparty,
Brothers Vermont. We therefore vacate the judgment confirming the award and direct that a new
judgment shall be entered confirming the award only to the extent that it imposes liability on
Brothers Nantucket. We affirm the judgment dismissing the Yankows' counterclaims and third-party
complaint.

Background. We summarize the facts as found by the motion judge and by the trial judge,
supplemented by uncontroverted testimony and other materials in the record.

The Yankows own and operate an inn known as the Cobblestone Inn in Nantucket, where they also
reside. On January 7, 1997, the Yankows entered into a standard form agreement (agreement)*fn3
with Brothers Nantucket for the performance of certain renovations to the inn. The agreement
listed Brothers Nantucket as the contractor and was signed by David Brookes on behalf of Brothers
Nantucket. Section 4.5.1 of the general conditions to the agreement provided that
any "controversy or [c]laim arising out of or related to the [agreement], or the breach thereof"
would be submitted to binding arbitration in accordance with the Construction Industry
Arbitration Rules of the American Arbitration Association (AAA).

At the time the parties entered into the agreement, Brothers Nantucket was a Massachusetts
corporation having its usual place of business in Nantucket. Brothers Vermont was a Vermont
Corporation with its usual place of business in Waitsfield, Vermont. Brothers Vermont had formed
Brothers Nantucket in August, 1996, in order to compete for local Nantucket building contracts
and to employ local Nantucket workers. Richard C. Brothers was president of both Brothers
Nantucket and Brothers Vermont.

A dispute arose with respect to the work performed at the inn and payment for that work.
Accordingly, on November 12, 1997, Brothers Nantucket filed a demand for arbitration with the
AAA, claiming unpaid bills in the amount of $78,414. On December 12, 1997, the Yankows filed an
answer and counterclaim for $49,900 which denied that the Yankows owed Brothers Nantucket any
money and further stated that:

"Respondent in counterclaim (Brothers Building Co.) substantially breached the contract in many
ways, including but not limited to failing to comply with many of its terms and failing to
deliver substantial completion in a timely fashion. Respondent in counterclaim also committed
many acts that constitute unfair or deceptive acts or practices within the purview of [G. L. c.]
93A."

On December 15, 1997, counsel for Brothers Nantucket sent a reply to the AAA, denying that it was
liable on the counterclaim. In an accompanying cover letter, counsel also asserted that the
counterclaim had been directed not against Brothers Nantucket, the claimant in the action, but
rather against Brothers Vermont, an entity that was not a party to the proceeding and, hence,
should be dismissed. More specifically, counsel stated:

"It appears that Respondent's Counterclaim is directed against only Brothers Building Co., Inc.,
an entity not a party to this proceeding. As Brothers Building Co., Inc., of Waitsfield, Vermont
has not filed a claim against Respondents, no 'counterclaim' can be filed against it. If I am
incorrect, please notify me immediately."

The AAA did not respond to this letter, but did schedule the matter for hearing. At the hearing,
counsel for Brothers Nantucket, consistent with his prior letter, made a motion to dismiss the
counterclaim on the ground that it had been asserted only against Brothers Vermont. The
arbitrator did not allow this motion but proceeded to hold four days of hearings with respect to
the claim and counterclaim. He also conducted a site inspection. Thereafter, on April 8, 1998,
the arbitrator issued an award finding that Brothers Nantucket was not entitled to recover
anything on its claim against the Yankows and, further, that both Brothers Nantucket and Brothers
Vermont were liable to the Yankows on their counterclaim for failure to perform or complete work
in accordance with the agreement. More specifically, the arbitrator found:

"Testimony given by [Brothers Building Co. of Nantucket, Inc.,] and by Brothers Building Co. of
Waitsfield, Vermont, Inc., indicate both companies were responsible for supervision of the
project, supplying the labor force, office duties, and sharing of profits. Therefore, I find that
Brothers Building Co. of Nantucket, Inc.[,] and Brothers Building Co. of Waitsfield, Vermont, Inc.
[,] are jointly liable for claims made by the Respondent."

The arbitrator awarded the Yankows $12,000 for "Costs due to late completion," $15,000 for "Cost
[s] to complete [the project]," and $22,900 for "Repairs due to substandard work including code
violation." The arbitrator made no mention of the G. L. c. 93A claim and stated that: "This award
is in full settlement of all claims and/or counterclaims submitted to this arbitration."

After this award was made, the plaintiffs commenced the instant lawsuit pursuant to G. L. c. 251,
§§ 12 and 13, to vacate or modify the award on the grounds that the arbitrator had exceeded his
authority in imposing liability on Brothers Vermont and also in including in his award an amount
for purported code violations. The Yankows filed an answer and counterclaims as well as a third-
party complaint against Richard C. Brothers (Brothers). The Yankows alleged in their
counterclaims and third-party complaint that the plaintiffs had breached their duty of good faith
and fair dealing and had also violated G. L. c. 93A in asserting a "separate corporate identity"
defense in the arbitration proceeding and in subsequently commencing the instant proceeding to
vacate or modify the arbitration award; further, the Yankows alleged that Brothers was personally
liable for these actions. After the plaintiffs had filed a motion to vacate or modify the award
and the Yankows had filed a cross motion to confirm the award, a Superior Court judge caused a
judgment to enter on June 1, 1999, confirming the award in its entirety. In an accompanying
memorandum, the judge explained that "[i]t was open to the arbitrator to cast liability on both
corporations jointly and severally," and that "I find no miscalculation of the damages." The
judge further ruled that the Yankows' counterclaims and third-party complaint should be
bifurcated and tried separately.

A trial on the counterclaims and third-party complaint was held before a different Superior Court
judge on September 29, 2000.*fn4 Following this trial, the judge entered an order directing that
judgment should enter dismissing the Yankows' counterclaims and third-party complaint. In
accompanying findings of fact and rulings of law, the judge ruled that, in entering into the
contract with Brothers Nantucket, the Yankows were acting as business persons, rather than as
individual consumers, and, hence, they could not assert a claim under G. L. c. 93A, § 9. The
judge further ruled that, to the extent the Yankows were asserting a claim under G. L. c. 93A, §
11, they had failed to show that the plaintiffs or Brothers had engaged in any "oppressive or
vexatious misuse of legal process" that could possibly constitute a violation of that section.
The judge also ruled that the plaintiffs by their conduct had not committed a breach of any duty
of good faith or fair dealing.

1. Confirmation of award. The plaintiffs claim that the arbitrator's award should not have been
confirmed because the arbitrator exceeded his authority in finding Brothers Vermont jointly
liable for the Yankows' damages even though Brothers Vermont was not a party to the agreement and
did not participate in the arbitration proceedings. We agree. It is well settled that "[a]
rbitration is a remedy created by statute which limits its availability to the parties to an
arbitration agreement." Rae F. Gill, P.C. v. DiGiovanni, 34 Mass. App. Ct. 498, 503 (1993). Here,
Brothers Vermont was not a party to the arbitration agreement.*fn5 The arbitrator, therefore, had
no power to find it liable under the agreement. See Computer Corp. of America v. Zarecor, 16
Mass. App. Ct. 456, 459-460 (1983) (arbitration may proceed only as to those parties who agree to
arbitrate).

The arbitrator nevertheless appeared to rely on a form of "alter ego" or "disregard of corporate
identity" theory in holding Brothers Vermont liable in this case. See My Bread Baking Co. v.
Cumberland Farms, Inc., 353 Mass. 614, 619 (1968); Lee v. International Data Group, 55 Mass. App.
Ct. 110, 117 n.7 (2002). Thus, the arbitrator found, not that Brothers Vermont was a party to the
agreement, formal or otherwise, but rather that Brothers Vermont was responsible with Brothers
Nantucket for "supervision of the project, supplying the labor force, [and performing] office
duties," and also for "sharing of profits." There was nothing in the agreement, however, that
permitted the arbitrator to reach any such result. To the contrary, the agreement provided that
the "contractor" was entering into the agreement. It did not provide that the contractor plus all
other entities that were somehow related to the contractor were entering into the agreement.*fn6

Nor does it appear in the record that Brothers Vermont otherwise agreed to submit any issue to
the arbitrator to decide. While the arbitrator referred in his award to "[t]estimony given by
[Brothers Building Co. of Nantucket, Inc.,] and by Brothers Building Co. of Waitsfield, Vermont,
Inc.," it appears that the arbitrator was simply attributing testimony presented by Brothers
Nantucket to Brothers Vermont. Nothing in the record suggests that Brothers Vermont separately
appeared and participated in the arbitration proceeding.

We therefore conclude that the arbitrator exceeded his authority to the extent that he imposed
liability on Brothers Vermont. This determination does not, however, preclude the Yankows from
pursuing a remedy against Brothers Vermont on the basis that Brothers Vermont is truly an alter
ego of Brothers Nantucket. The Yankows can bring a proceeding against Brothers Vermont to enforce
the award they have obtained and attempt, in that enforcement proceeding, to prove that Brothers
Vermont is actually an alter ego of Brothers Nantucket.*fn7 See G. L. c. 251, § 14 (arbitration
award, if confirmed, may be enforced as any other judgment); Heacock v. Heacock, 402 Mass. 21, 23
n.2 (1988), S.C., 30 Mass. App. Ct. 304 (1991) (valid final judgment is conclusive on parties
and "their privies"). All we hold is that the arbitrator had no authority to reach such a result
on his own in this case, where Brothers Vermont was not a party to the agreement and did not
otherwise agree to have its alleged alter ego status determined by the arbitrator. See School
Comm. of Hanover v. Hanover Teachers Assn., 435 Mass. 736, 740 (2002) (arbitrator's award must
draw its essence only from contract at issue); Parekh Constr., Inc. v. Pitt Constr. Corp., 31
Mass. App. Ct. 354, 359 n.8 (1991) ("Whether the parties have agreed to arbitrate is a matter to
be decided finally by the court and not by the arbitrator"). See also Orion Shipping & Trading
Co. v. Eastern States Petroleum Corp., 312 F.2d 299, 300-301 (2d Cir. 1963) (arbitrator exceeded
his authority in relying on alter ego theory to impose liability under agreement on an entity
that was not a party to the agreement).

The plaintiffs additionally claim that the arbitrator exceeded his authority in including in the
damages he awarded an amount for "[r]epairs due to substandard work including code violations,"
even though he had prevented the Yankows from offering certain expert testimony with respect to
the code violations they were alleging. The plaintiffs claim that, by excluding the Yankows'
evidence, the arbitrator induced Brothers Nantucket to believe that there was no issue in the
case with respect to code violations and, hence, not to offer any contrary evidence. These
contentions are "completely without any factual foundation in the record." Bay State York Co. v.
Canter Constr. Co., 5 Mass. App. Ct. 192, 195 (1977). We, therefore, reject these contentions as
a proper basis for concluding that the arbitrator somehow exceeded his authority in determining
the amount of his award. See Farm Constr. Serv., Inc. v. Robinson, 21 Mass. App. Ct. 955, 956
(1986).

2. Dismissal of counterclaims and third-party complaint. The Yankows claim that the trial judge
erred in dismissing their counterclaims against the plaintiffs and also their third-party
complaint against Brothers, because they introduced overwhelming evidence that Brothers Vermont
was involved in the renovation project from the beginning; hence, the Yankows claim, there was no
basis for the plaintiffs and Brothers to assert a "separate corporate identity" defense for the
first time at the arbitration hearing, and then to commence litigation to vacate the arbitration
award.*fn8 The Yankows further claim that the judge erred in dismissing their counterclaims and
third-party complaint because they introduced evidence that neither of the plaintiffs was a
licensed home improvement contractor during the renovation activities, as required by G. L. c.
142A.

We tend to agree that it was hypertechnical for Brothers Nantucket to assert at the arbitration
hearing that the Yankows' counterclaim against it (as distinct from Brothers Vermont) should be
dismissed because the counterclaim named Brothers Vermont as the "Respondent in counterclaim,"
rather than Brothers Nantucket. It is well settled that substantive rights should not be
determined by such matters of form. See, e.g., Pizer v. Hunt, 250 Mass. 498, 504 (1925) ("A party
to an action has no vested right to have a case decided and determined upon a form of procedure
which may have been inadvisedly or mistakenly chosen").

Nevertheless, the mere assertion of such a defense at an arbitration hearing or in a subsequent
action to set aside or modify an arbitration award is not grist for a claim of violation of G. L.
c. 93A or breach of the duty of good faith and fair dealing, even assuming that some litigation
tactics might properly give rise to such claims, a question the Supreme Judicial Court has not
yet decided. See Schubach v. Household Fin. Corp., 375 Mass. 133, 135 n.3 (1978) (declining to
decide whether finance company's alleged policy of instituting litigation in venues inconvenient
to debtors so as to precipitate defaults might constitute violation of G. L. c. 93A). We note
that the rules of civil procedure already provide a specific sanction for instances where an
attorney has filed a pleading on behalf of a party without a belief that there is "a good ground
to support [the pleading]." Mass.R.Civ.P. 11(a), 365 Mass. 753 (1974).

We further note that the trial judge in this case expressly found that "there is no evidence that
Brothers Nantucket, Brothers Vermont, or Richard C. Brothers have withheld payment intentionally,
nor have they disregarded any contractual arrangements with the Yankows." The Yankows have made
no showing that this finding was clearly erroneous or that they were precluded from submitting
any evidence that could have led to a different finding. Indeed, for the reasons we have stated,
the plaintiffs' motion to vacate or modify the arbitration award was not frivolous; we have
concluded that one of the grounds on which it was based was meritorious. Hence, the mere bringing
of the motion did not warrant a finding of bad faith or violation of G. L. c. 93A. Compare
Commercial Union Ins. Co. v. Seven Provinces Ins. Co., 217 F.3d 33, 40-44 (1st Cir. 2000). Nor
have the Yankows made any sufficient showing that they were entitled to prevail on their
counterclaims and third-party complaint merely because neither of the plaintiffs was registered
as a home improvement contractor. Indeed, it does not appear from the record that the Yankows
included any such claim in their counterclaims or third-party complaint, or that they made any
such argument to the trial court. They are therefore precluded from pursuing the claim here. See
Cottam v. CVS Pharmacy, 436 Mass. 316, 320 (2002) ("Having failed to raise these [claims] below,
CVS cannot assert them now").

We therefore conclude that the trial judge properly dismissed the Yankows' counterclaims and
third-party complaint. See Van Dyke v. St. Paul Fire & Marine Ins. Co., 388 Mass. 671, 675-678
(1983); Gulezian v. Lincoln Ins. Co., 399 Mass. 606, 613 (1987).

Conclusion. The judgment confirming the arbitration award is vacated, and a new judgment shall
enter confirming the award only to the extent that it imposes liability on Brothers Building Co.
of Nantucket, Inc. The judgment dismissing the Yankows' counterclaims and third-party complaint
is affirmed.

So ordered.


Opinion Footnotes

*fn1 Brothers Building Co., Inc.

*fn2 Robin Yankow.

*fn3 Specifically, the agreement is a "Standard Form of Agreement Between Owner and Contractor"
of the American Institute of Architects (AIA), AIA document A111 (1987 ed.)

*fn4 Prior to this trial, a different Superior Court judge allowed a motion by the Yankows for
summary judgment on their counterclaims and third-party complaint, but after this judge had
retired, another Superior Court judge vacated the judge's order and again directed that a trial
should be held in the matter.

*fn5 We recognize that next to the printed word "contractor" on the signature page of the
agreement were written the words, "Brothers Building Co., Inc." which was the corporate name for
Brothers Vermont, rather than Brothers Nantucket. David Brooks, who signed the agreement on
behalf of Brothers Nantucket, testified at the trial of this matter, however, that Keith Yankow,
rather than Brooks himself, had written these words on the signature page and may have done so
after Brooks had signed the agreement. Apparently crediting this testimony, the judge
specifically found that Brooks had executed the agreement "on behalf of Brothers Nantucket,"
which was named as the contractor in the agreement, rather than on behalf of Brothers Vermont.
The Yankows have made no claim on appeal that this finding was "clearly erroneous" within the
meaning of Mass.R.Civ.P. 52(a), as amended, 423 Mass. 1402 (1996).

*fn6 Section 13.2.1 of the general conditions of the agreement provided that "[t]he Owner and
Contractor respectively bind themselves, their partners, successors, assigns and legal
representatives to the other party hereto and to partners, successors, assigns and legal
representatives of such other party in respect to covenants, agreements and obligations contained
in the Contract Documents." The Yankows have not claimed, however, that the arbitrator could
properly rely on this section in holding Brothers Vermont liable under the agreement, and nothing
in the record suggests that Brothers Vermont was in fact a partner, successor, assign or legal
representative of Brothers Nantucket. Rather, the most the record suggests is that Brothers
Vermont was the corporate parent of Brothers Nantucket.

*fn7 The instances in which courts disregard separate corporate entities are rare. See Evans v.
Multicon Constr. Corp., 30 Mass. App. Ct. 728, 732-733 (1991).

*fn8 The Yankows additionally complain that the judge erred in allowing a pretrial motion in
limine to exclude all evidence of alleged unfair conduct occurring during the construction
process prior to the arbitration hearing. The Yankows, however, have failed to demonstrate that
they suffered any prejudice as a result of the judge's allowance of that motion. See G. L. c.
231, § 119. More specifically, the Yankows have failed to demonstrate that they were thereby
improperly prevented from presenting any evidence which could possibly have strengthened their
claim that the plaintiffs breached their duty of good faith and fair dealing, or violated G. L.
c. 93A, merely by asserting the separate corporate identity defense at the arbitration hearing
and by subsequently commencing the instant action to set aside or modify the arbitrator's award.
RISER ADKISSON LLP, 100 Bayview Circle, Suite 210, Newport Beach, CA 92660, Ph: 949-200-7284, Fax: 877-296-0678, jay --at-- risad.com - http://www.risad.com - http://www.jayadkisson.com - http://www.captiveinsurancecompanies.com - http://www.eaibook.com - http://www.calejl.com

Purchase our book "Asset Protection: Concepts and Strategies" at
http://www.amazon.com/gp/product/0071432167?ie=UTF8&tag=httpassetproc-20&linkCode=as2&camp=1789&creative=9325&creativeASIN=0071432167?
User avatar
Riser Adkisson LLP
Riser Adkisson LLP
Riser Adkisson LLP
 
Posts: 1115
Joined: Thu Nov 13, 2008 8:06 pm
Location: California, Georgia, North Carolina, Oklahoma, and Texas

Return to Massachusetts

Who is online

Users browsing this forum: No registered users and 1 guest